TaskIn ChargeTimelineProgress
Outline the process and timeline for the self study (Preface)Volunteer Group30/11/23Completed
Introducing the IB Self Study to staffEach Programme Coordinator(9) January 2024Completed
Progress reportVolunteer groupBiannual updateUp to date by Jan 31st
School ProfileEP/CA and MarComAnnual updateUp to date by Jan 31st
Sharing Progress to All StaffVolunteer Group7 March 2024Completed
Category A (Draft)Volunteer group28 March 2024Completed
Category C (Draft)Volunteer group28 March 2024Completed
Category D (Draft)Volunteer group28 March 2024Completed
“Purpose” Criterion CompletedEach Programme Coordinator31 May 2024Completed
“Environment” Criterion CompletedEach Programme Coordinator20 September 2024Completed
Category A strengths and growth areas for continuous improvement1/3 of staff including parent and student representatives.26 September 2024Completed
Category C strengths and growth areas for continuous improvement1/3 of staff including parent and student representatives.26 September 2024Completed
Category D strengths and growth areas for continuous improvement1/3 of staff including parent and student representatives.26 September 2024Completed
“Culture” Criterion CompletedEach Programme Coordinator29 November 2024
Summary from analysis of identified major student learner needs.Volunteer groupDecember 2024
Schoolwide action plan. All IBO Programmes documents are ready. These include : Preliminary review document, Self-study document, PDP documentVolunteer Group and Each Programme Coordinator21 March 2025
“Learning” Criterion CompletedEach Programme Coordinator27 March 2025

WASC Timeline IB Timeline


15 May 2025
Preliminary review document submission deadline

01 August 2025
Self-study questionnaire submission deadline

15 September 2025
Evaluation Visit